Details of university classroom renovations can be found below:

Building Room
Number
Description of Work Target
Start Date
Target
End Date
Status
Ackerson 123 Technology Upgrade May-18 Aug-18 Completed
Boyden 100 Technology Upgrade May-16 Sep-16 Completed
Boyden 413 Technology Upgrade May-18 Aug-18 Completed
Bradley 311 Learning Space Renovation & Technology Upgrade May-17 Sep-17 Completed
Bradley 312 Learning Space Renovation & Technology Upgrade May-17 Sep-17 Completed
Bradley 403 Technology Upgrade May-17 Sep-17 Completed
CLJ  202 Learning Space Renovation & Technology Upgrade Dec-17 Jan-18 Completed
CLJ 392 Learning Space Renovation & Technology Upgrade Mar-18 Mar-19 Completed
Conklin 100 Technology Upgrade May-16 Sep-16 Completed
Conklin 237 Learning Space Renovation May-18 Jun-18 Completed
Conklin 238 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 342 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 343 Learning Space Renovation May-18 Aug-18 Completed
Conklin 344 Learning Space Renovation May-18 Aug-18 Completed
Conklin 345 Learning Space Renovation May-18 Aug-18 Compelted
Conklin 346 Learning Space Renovation & Technology Upgrade May-17 Sep-17 Completed
Conklin 348 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 349 Learning Space Renovation May-18 Aug-18 Completed
Conklin 350 Learning Space Renovation May-18 Aug-18 Completed
Conklin 351 Learning Space Renovation May-18 Aug-18 Completed
Conklin 352 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin  424 Technology Upgrade May-18 Aug-18 Completed
Conklin 445 Learning Space Renovation May-16 Sep-16 Completed
Conklin  446 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 447 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 448 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Conklin 449 Technology Upgrade Dec-17 Jan-18 Completed
Conklin  451 Learning Space Renovation May-18 Aug-18 Completed
Conklin  452 Learning Space Renovation May-18 Aug-18 Completed
Conklin 453 Learning Space Renovation May-18 Aug-18 Completed
Conklin 454 Learning Space Renovation May-18 Aug-18 Completed
Conklin 455 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
Cyber Lounge (PRCC) 351 Learning Space Renovation & Technology Upgrade Aug-16 Nov-16 Completed
Engelhard 209 Learning Space Renovation May-17 Sep-17 Completed
Engelhard 211 Learning Space Renovation May-17 Sep-17 Completed
Engelhard 213 Learning Space Renovation May-16 Sep-16 Completed
Engelhard 215 Learning Space Renovation Dec-17 Jan-18 Completed
Engelhard 309 Learning Space Renovation & Technology Upgrade Aug-17 Sep-17 Completed
Engelhard 311 Learning Space Renovation & Technology Upgrade May-16 Sep-16 Completed
Hahne 322 Construction Project July-16 Jan-17 Completed
Hahne 411 Construction Project July-16 Jan-17 Completed
Hahne 422 Construction Project July-16 Jan-17 Completed
Hahne 421 Construction Project July-16 Jan-17 Completed
Hill 102 Learning Space Renovation May-16 Sep-16 Completed
Hill 103 Learning Space Renovation TBD TBD  Pending
Hill 104 Technology Upgrade May-16 Sep-16 Completed
Hill 105 Learning Space Renovation TBD TBD Pending
Hill 107 Learning Space Renovation May-18 Sep-18 Completed
Hill  108 Technology Upgrade May-17 Sep-17 Completed
Hill 124 Learning Space Renovation & Technology Upgrade Dec-16 Jan-17 Completed
Hill 126 Learning Space Renovation & Technology Upgrade Dec-16 Jan-17 Completed
Hill 125 Learning Space Renovation & Technology Upgrade May-16 Sep-16 Completed
Hill 127 Learning Space Renovation & Technology Upgrade May-16 Sep-16 Completed
Hill 201 Learning Space Renovation May-16 Sep-16 Completed
Hill 202 Learning Space Renovation May-17 Sep-17 Completed
Hill  203 Learning Space Renovation May-16 Sep-16 Completed
Hill 204 Learning Space Renovation & Technology Upgrade May-16 Sep-16 Completed
Hill  205 Learning Space Renovation May-17 Sep-17 Completed
Hill 208 Learning Space Renovation May-16 Sep-16 Completed
Hill 209 Learning Space Renovation May-16 Sep-16 Completed
Hill 210 Learning Space Renovation & Technology Upgrade May-16 Sep-16 Completed
Hill 215 Learning Space Renovation May-15 Aug-15 Completed
Hill 216 Learning Space Renovation May-15 Aug-185 Completed
Hill  217 Learning Space Renovation & Technology Upgrade May-18 Aug-18 Completed
LSC 103 Technology Upgrade May-18 Aug-18 Completed
LSC 130 Learning Space Renovation & Technology Upgrade Sep-17 Jan-18 Completed
Smith B22 Learning Space Renovation May-17 Sep-17 Completed
Smith B23 Learning Space Renovation May-17 Sep-17 Completed
Smith B24 Learning Space Renovation May-17 Sep-17 Completed
Smith B25 Learning Space Renovation May-17 Sep-17 Completed
Smith B26 Learning Space Renovation May-17 Sep-17 Completed
Smith B27 Learning Space Renovation May-17 Sep-17 Completed
Smith 103 Learning Space Renovation May-17 Sep-17 Completed
Smith 104 Learning Space Renovation May-17 Sep-17 Completed
Smith 220 Technology Upgrade Feb-16 May-16 Completed